Another day of hard work lays behind us. Again we distributed our workforce on to two subjects: in the morning Muriel and Julius finished up on the measuring at KYC and Simiyus current flat.
At lunchtime the terrain surveyers visited Felix and Sepp at Sweet Angels, where the bridge workers had rounded the wood construction with clay from the river.
In the afternoon we did a little switcheroo and Julius went back to KYC with Felix. We took a quite a few more photos for scale and filmed a couple of small videos for us to remember / show to others. Sadly, we are not able to post any videos here for now, we might add them later! In the meantime enjoy this:
At Sweet Angels Sepp and Muriel helped complete the arch structure. Again there was a huge community support and interest in the ongoing project. Now everything left to do is put up some Handrails and stairs, and then strip the formwork. We are confident to be able to complete this by next week!